BDCC leaders went checking the site of Package CW2 – Upgrading and Rehabilitating An Duong Water Treatment Plant under Rehabilitating and Upgrading Project of Hai Phong Water Supply System (stage 2)

05On 05/04/2018 morning, Mr. Nguyen Trong Khai – General Director, Mr. Nguyen Van An – Deputy General Director with leaders and experts of BDCC functional departments went checking the site of Package CW2 – Upgrading and Rehabilitating An Duong Water Treatment Plant under Rehabilitating and Upgrading Project of Hai Phong Water Supply System (stage 2).

General Director Nguyen Trong Khai checking and instructing the construction work on package site

 

Commenced on 05/01/2018, lasting 03 months of active deploying of construction, BDCC, up to now, has completed 15,7% of contractual value, ensuring the schedule as requested. Many items have met the requirement of progress as slurry tanks 1, 2; receiving partition, discharge separator chamber, chemical house…; concrete driven piles have been speeded up; cluster of 2-layer filter tanks have reached 141/288 of pile centers; cluster of fresh water stations, filter pumping station, control room, stabilization station have reached 18/115 of pile centers; 60% completed: slab concrete  for tank No.1, 25% of slab concrete  for tank 2; placing the bracing for foundation of chemical house; performing the submission and order making of steel pipes to the site; making plan, method of construction for underground piping as well as in corporation with execution teams to install and connect….

 

At site, General Director dignified the spirit of activeness to overcome the difficulties of execution units as well as asked them to pay more attention to safety and hygiene, completion of sign system on site, and strictly cooperating with other parties in the joint venture as Salcon (Malaysia) to ensure the progress and work quality.

 

Bài viết liên quan

Bach Dang Construction Corporation won the champio...
views 23
In response to the culture, sports movements in order to welcome 60-year tradition day anniversary of Viet Nam Construction Industry (29/04/1958 - 29/...
Bach Dang Construction Corporation-JSC. launched t...
views 37
On 18/4/2018 morning, at the site of Package CW2 - Upgrading An Duong Water Treatment Plant under Rehabilitating and Upgrading Project of Hai Phong Wa...
Bach Dang Construction Corporation – TOPTEN ...
views 31
On 13th and 14/4/2018 in Hanoi, Vietnamese Economic Times held the Festival of Golden Dragon Enterprise (17th) and Vietnam Power Trademark (13th) with...
Bach Dang Construction Corporation-JSC received th...
views 22
On 06/04/2018 morning, at Hai Phong Conventional Center, VCCI - Hai Phong branch held the Conference of Business in Northern Coastal Area 2018. Mr. Bu...
BDCC leaders went checking the site of Package 3.2...
views 13
On 28/03/2018 morning, Mr. Nguyen Trong Khai - BDCC General Director with Mr. Luu Quang Bon - Deputy General Director, leaders and experts of...