Up to November 26th 2013, Bach Dang Construction Corporation has completed 02 asphalt layers (10cm), reaching around 140,000 m2 of road surface, and total length of almost 10,000m. The executed volume reached 75 billion VND. Currently, the progress of handing over the site from the main Contactor is interrupted which does not meet the construction schedule of Bach Dang Construction Corporation. Project Management Board and construction Companies were required to cooperate with the main Contactor – Doosan to push up the progress of handing over the site in order to ensure the progress of the project.
Package A6 (one of 8 packages of Noi Bai – Lao Cai highway project) is the way to pass through Van Yen district, Yen Bai province with a total length of 40 km (from Km159 to Km199). According to the design, the roadbed is 24m wide, consists of 4 lanes, 2 emergency stopping lanes, median strips, safety strips and roadsides. The starting point of Noi Bai-Lao Cai Project is an intersection between Noi Bai-Ha Long highway and National road No.2, the ending point is connected with Kunming-Ha Khau highway of China at Quang Kim commune, Bat Xat district, Lao Cai province of Vietnam. This is an extremely important project belonging to Kunming-Hai Phong transport corridor under Mekong sub-regional cooperation Programs. It is also the project with the largest scale of length and total capital investment in Vietnam at present.