General Director of BDCC Inspected Construction Site of Mong Duong 1 Thermal Power Plant Project.

General Director inspected the quality and progress of the construction site


After construction site inspection and the meeting with Hyundai general contractor, General Director held a meeting to review progress and construction plan for the items of Civil Package A and Building A. Up till now, the Civil Package A has reached 80% and Building A has reached nearly 40%. At the meeting, Bach Dang Construction Joint Stock Company No.201; Bach Dang 234 Construction Joint Stock Company;  Bach Dang 5 Joint Stock Company were required to increase manpower, and equipment to overcome existing problems and ensure the project’s overall progress.
 

Some images of  BDCC’s General Director inspected the construction site







Trả lời

Email của bạn sẽ không được hiển thị công khai. Các trường bắt buộc được đánh dấu *