After construction site inspection and the meeting with Hyundai general contractor, General Director held a meeting to review progress and construction plan for the items of Civil Package A and Building A. Up till now, the Civil Package A has reached 80% and Building A has reached nearly 40%. At the meeting, Bach Dang Construction Joint Stock Company No.201; Bach Dang 234 Construction Joint Stock Company; Bach Dang 5 Joint Stock Company were required to increase manpower, and equipment to overcome existing problems and ensure the project’s overall progress.
NEWS & EVENTS
General Director of BDCC Inspected Construction Site of Mong Duong 1 Thermal Power Plant Project.
General Director inspected the quality and progress of the construction site
Some images of BDCC’s General Director inspected the construction site