General Director Pham Tien Hung together with leaders of Ha Tinh province and the Owner were inspecting the construction site
After construction site inspection and having a meeting with PetroVietnam and leaders of Ha Tinh people’s Committee, General Director held a meeting to review progress of the project items of Vung Ang 1 Thermal Power Plant. Up till now, the works of the Contract have basically completed accordance to schedule, quality, labor safety as committed, and the trial test of oil fired heating Boiler No.1 has been successful (17th August 2013), which was highly appreciated by the Owner. The Project Management Board was required to strengthen management and drastically instruction for construction Companies to focus on manpower, accelerate the progress to ensure coal-fired schedule of the Plant on 06th December 2013.
General Director Pham Tien Hung attended the regular meeting in October 2013 at Vung Ang-Quang Trach Power Project Management Board
Successful trial test of oil fired heating Boiler No.1