Bach Dang
Construction Corporation performs some main works of this EPC Contract (Design,
Equipment Supply, Installation, construction, test commissioning, Technology
Transfer) of the Project.
The scope of work
consists of Coal and Oil supply systems; Storage for fuel and materials; power
distribution station; and some other Works with the total estimated value of 700
bil. VND. The package EPC proposed tobe started in early September, 2009 and
completed after 42 months.
Uong Bi thermal
power Plant – 600MW capacity Built by Bach