Completion of Packages under Dung Quat Refinery

Bach Dang have just handed over to TPC packages CV5 and B1/B3 under the construction of Dung Quat Refinery Project. Total amount of these Packages is 21.7 millions dollars.

Over-view of Dung
Quat Refinery Project

Packages B1 B3 is
in Process Unit including 17 work items: one Center Control Complex, 10
Substations, 3 Process Interface
Buildings, 2 Marshalling Rack Rooms
and one Laboratory in Process Unit of Dung Quat Refinery. The execution and
hand-over of these buildings met the requirement of schedule. These buildings
were entering commissioning phase.

CV5 is in the
Product Storage Area with product storage tank foundation, 9km road to pipeline
route, 5km transportation road, 9km waste water collect pipeline, 2,200m2 square
of Jetty, 14,000m2 concrete foundations and other work items completed.  These items were put into commissioning phase.