Lach Tray – Ho Dong is the main arterial road with cross section of 100m connected from Lach Tray street (main road) to Ho Dong (the south of the City) and it was invested by Urban Development – Investment & Trading one member Co., Ltd. Bach Dang Construction Corporation is the main contractor of Package 3.D2-T100: “Construction of sub-base, drainage, sewerage, pumping stations, trees and equipment installation for section from km 5+900 to Km6 +694 (794m) and the contract worth 76.685 billion VND.
Compacting macadam aggregate type 1 for section from Km6+158 to Km6 +330 at the right side
Up to date of May 14th 2014, nearly 600/794m of construction site was handed over to BDCC. After nearly 01 month of construction (from April 17th 2014), the Corporation has requested the construction companies to work in accordance to schedules.
Construction of macadam aggregate type 2 for section from Km6+080 to Km6 +360 at the left side
In the coming time, the Corporation continues to carry out raw asphalt course with major quantity of 17.300m2 to ensure completion of progress target according to technical stops as agreed with the Owner.
Construction of curbs and concrete slabs
Stock Yard of macadam aggregate type 2 for construction
Casting concrete slab and curbs
Ищите в гугле