On the 4th December 2009, at BDCC’s head office organized the Contract Signing Ceremony by and between HABECO HaiPhong – the Owner and Bach Dang Construction Corporation – Main Contractor for Package 8 “Construction of workshop, office, infrastructure and landscaping” under the Investment, construction of Ha Noi Beer Factory Project in Hai Phong with capacity 25 mil. liters per year (stage 1) and open 50 mil. liters per year (stage 2).

 This Contract
valued 64,800,000,000.0 VND and started on 21st December 2009 with construction schedule 189 days.


Contract Signing
Ceremony of Ha Noi Beer Factory Project in Hai Phong.