Mr. Le Khac Nam – Vice Chairman of Hai Phong People’s Committee checkedthe schedule of Viet Tiep Friendship Hospital – branch 2 and Hai Phong Sailing Training Area Project

In the morning 20/10/2014 morning, Mr. Le Khac Nam – Vice Chairman of Hai Phong People’s Committee and the departments and branches of City went to check the construction schedule at the site of Viet Tiep Friendship Hospital – Branch 2 in An Dong commune (An Duong district) and Sailing Training area in Minh Duc town (Thuy Nguyen district).

Mr. Le Khac Nam – Vice Chairman of Hai Phong People’s Committee inspected the site of Sailing Training area

After inspecting the jobsite, the Vice Chairman held the meeting to review the construction schedule and made conclusion for the each project.


Mr. Le Khac Nam – Vice Chairman of Hai Phong People’s Committee chaired a meeting at Viet Tiep 2 project

At Viet Tiep Friendship Hospital project – branch 2: the Vice Chairman recognized, praised and highly appreciated the determination of the Project Management Unit and the contractor also (JV of Bach Dang Construction Corporation and Hai Phong Youth Joint Stock Company) who implemented well the requirements of the project and met the requirements of schedule, quality and safety. This is one of the key projects of the city, meant especially important, when being completed will meet the urgent demand for hospital beds, medical care for people in the city and surrounding areas. He requested the PMU and contractor in the near future, focus more, speed up more construction schedule to ensure that in the middle of 2015 some work items of the project will be put into use as planned.


Mr. Le Khac Nam – Vice Chairman of Hai Phong People’s Committee chaired a meeting at Sailing training area project

In the sailing training area project: The Vice Chairman recorded, highly appreciated the attempt, effort of the Contractor – Bach Dang Construction Corporation – JSC in terms of difficulties in construction sitejob, the delay of disbursement of project, … but the Corporation has determined to accelerate construction schedule to meet the requirements for the quality and progress of the project.  He requested the PMU and city department also in the near future to solve problems in terms of job plan and capital source to be handed over to the contractor in order to accelerate construction schedule and complete emergency work items such as: Stand, operation house, residential house for coaches and athletes, … to promptly serve the National Sport Congress on 25/11/2014.

Photos of City Leaders visited and checked the construction site of projects:


Inspection delegate in Viet Tiep 2 Hospital project


Inspection delegate in Sailing training area project


Operation house and residential house for coaches and athletes basically completed