Bach Dang Construction Corporation honourably participating the construction of Dung Quat Refinery

Bach Dang Construction Corporation honourably carry out Packages B1/B3 and CV5 with its total amount of 21 millions UDS under the construction of Dung Quat Refinery Project.

 Packages B1/B3
include 17 work items: one Center Control Complex, 10 Substations, 3 Process
Interface Buildings,
2 Marshalling Rack Rooms and one Laboratory in Process Unit of Dung Quat
Refinery. The execution and hand-over of these buildings met the requirement of
schedule.

CV5 is in the
Product Storage Area. Scope of work for CV5 is Earthworks, Underground Piping
Works, Storage Tanks Foundation Works, Construction of Pipe Sleepers, Road
works & Drainage, Tank Farm Surface Finishing & Bund walls, Pipeline
Route 10.2 km long from Process Area to Product Storage Area & 2.4km long
from Product Storage Area to Jetty. Total price of CV5 Package is USD 13.945
millions. All of the work items of this Package were completed and handed over
to Technip Consortium in December 18th
2008.

In order to carry
out the above said Packages, Bach Dang Construction Corporation promptly set up
2 Project Management Boards working in the Process Unit and Product Storage
Area. During the critical period from March to July, 2007, total of 1.500 – 1.600
personnel were mobilized to the Site. Moreover, the works continuously carried
out with enthusiastic and diligent working spirit of personnel as well as
management boards despite the hard weather condition in Dung Quat. Thanks to
the direction and kind attention of Managers in head office, salary was paid
regularly and working condition was improved. Personnel displayed a good
tradition of Bach Dang Construction Corporation by doing well their task during
the construction of this Project.

antalya bayan escort
Free Porn