Ceremony of granting Decision for BDCC youth’s typical work – chimney foundation of Mong Duong Thermal Power Plant

   

Chimney foundation was constructed by BDCC youth

Chimney foundation was placed on 110 bored pile heads D = 800 mm with a depth of 60m, diameter of 26m and the height of foundation grid is 3.3 m. Total concrete weight is 2000m3; rebar quantity is 200 tons and 245m2 of formwork which is a  base  for chimney sharp with height of 205m. Construction procedures and close supervision was made by BDCC to ensure progress, quality, and labor safety.

The chimney foundation is a key work of Mong Duong 1 thermal power plant. According to the main contractor HDEC, construction time is 24 days beginning from 17th February 2013 and completing on 15th March 2013. It was completed 05 days earlier as required. Under close management of the Project Management Board’ leaders and the efforts and enthusiasm of 50 workers and youth members of BDCC, the work which accounts for 95% of the contract value nearly 7 billion VND and profit is more than 350 million VND.

Attending the ceremony were Mr. Le Tri Vu – deputy permanent secretary of Hai Phong Youth Union, Mr Tran Huy Hoang – Secretary of BDCC’s Youth Union, Mr. Nguyen Xuan Long – Site Manager of Civil Package A – Mong Duong 1 thermal power project, Mr Tran Huy Thang – Director of Bach Dang 234 construction Joint Stock Company, Mr Pham Trung Cuong – Secretary of BDCC head office’s Youth Union, Mr Vu Thanh Nam – Secretary of Mong Duong Project Management Board’ Youth Union and all youth members of BDCC’s head office and Mong Duong Project Management Board’s.


Mr Le Tri Vu – Deputy Secretary of Hai Phong Youth Union  granted Decision and Certificate of Hai Phong City youth’s typical work  for Mong Duong Project Management Board’s Youth Union  branch
 

Mr Tran Huy Hoang – Secretary of BDCC’s Youth Union granted presents to union members of Mong Duong Project Management Board for their achievement of Youth Union movement
   

 

Ceremony of granting Certificate for BDCC youth’s typical work

Completion of “Chimney foundation” by Mong Duong Project Management Board’s youth union in particular and BDCC’s in general is one of the activities for celebration of 55 year traditional anniversary of Bach Dang Construction Corporation (31/08/1958 – 31/08/2013).