Completion of Packages under Dung Quat Refinery

Over-view of DungQuat Refinery Project

Packages B1 B3 isin Process Unit including 17 work items: one Center Control Complex, 10Substations, 3 Process Interface Buildings, 2 Marshalling Rack Roomsand one Laboratory in Process Unit of Dung Quat Refinery. The execution andhand-over of these buildings met the requirement of schedule. These buildingswere entering commissioning phase.

CV5 is in theProduct Storage Area with product storage tank foundation, 9km road to pipelineroute, 5km transportation road, 9km waste water collect pipeline, 2,200m2 squareof Jetty, 14,000m2 concrete foundations and other work items completed.  These items were put into commissioning phase.