Contract Signing of Hai Phong Rainwater Drainage and Waste Water Project and Solid Waste Management – Phase I

Package A1: Construction of sewage water treatment: line 1, line 4, line 5 and the path to Vinh Niem waste water treatment plant – construction investment project of the rainwater and wastewater drainage component under Hai Phong Rainwater Drainage Project and Solid Waste Management – Phase I.

The Project owned by Haiphong People’s Committee, the funding for projects from ODA loans of Japan International Cooperation Agency (JICA) and reciprocal of Hai Phong budget.

Scale Package: Construction of two culvert covers/pressure wastewater collection and transfer wastewater to Cho Hang Pumping Station and a sewer line transporting from Cho Hang to Vinh Niem wastewater treatment plant including reinforced concrete gravity sewer DN800: 740m, DN1000: 313.5 m; HDPE pressure sewer DN1000: 2.635m, DN630: 542m; Ductile Iron pressure sewer pipe DN1200mm: 2.147m.

Package value: 366,926,465,649 VND (excluding inflation reserve and equipment import duties), construction period of 36 months after commencement.

Trả lời

Email của bạn sẽ không được hiển thị công khai. Các trường bắt buộc được đánh dấu *