On December 20, 2023, Bach Dang Construction Corporation – Joint Stock Company signed a construction contract (Phase 1) for the Construction of the road connecting DT.261 to DT.266 project, with a total value exceeding 92 billion VND.
The project is located in Pho Yen City and Phu Binh District, Thai Nguyen Province, and is under the management of the Project Management Board for the Investment and Construction of Provincial Transportation Projects in Thai Nguyen Province.
Project Scale:
The investment project for the construction of the road connecting DT.261 to DT.266 has a total investment of nearly 400 billion VND. The first phase is scheduled to be implemented from 2023 to 2024.
Technical grade: Main urban road;
Design speed Vtk= 60 Km/h
Cross-sectional scale of the section from Km0+0.0 to Km0+781.50: Bn=47.0m, including:
Roadway width Bm= 2×15.5m = 31.0m
Sidewalk width Bh= 2×6.0m = 12m
Median strip width Bpc=4.0m
Route length: 2,039.14m, with a segment passing through Pho Yen City of 536m and a segment passing through Phu Binh District of 1,503.14m. Design includes shaded greenery along the route, traffic safety signs, installation of lighting systems, cross-road drainage ditches, sidewalks, median strips, and a rainwater drainage system.
The project commenced on December 30, 2023, and is expected to be completed on June 26, 2024.