Contract Signing Ceremony of Package NT-1.5B – Coastal Cities Environmental Sanitary Project – Nha Trang City Sub-Project


Contract Signing Ceremony of Package NT 1.5B

The package NT-1.5B – Coastal CitiesEnvironmental Sanitary Project – Nha Trang City Sub-Project invested by KhanhHoa Provincial People’s Committee will address the frequently flooded areas inthe central area, the northern area of the Cai River and in the southern area. Itprevents wastewater flowing into the sea, and upgrades the lanes and smalltowns, and tackles environmental pollution by wastewater collection systemincluding public sewer and drain sump.

Construction works include: 02 pumpingstations 170m3/h and 120m3/h, Box culvert 2mx3m with total length of 1742m,barrels with sewer pipes from D800, D1000, D1200, D1500, D2000 with totallengths of 1800m. Pressure pipelines HDPE D300, D400 with total length of 1690m,Pipes uPVC D200 with total length of 970m.

Contract Value: 114.421.647.301 VND and 535,043USD

Construction period: 868 days.