General Director of Bach Dang Construction Corporation attended Steam Turbine #2 Casing Lifting Ceremony – Mong Duong 1 Thermal Power Plant


General Director Pham Tien Hung attended the Steam Turbine #2 Casing Lifting Ceremony

Equipment system of Unit 2 (turbine # 2) is placed on turbine foundation made of reinforced concrete with height of 16m – executed by Bach Dang Construction Corporation in 06 months’ time and the advanced technology of PERI formworks were applied for this item which satisfied progress, quality and safety requirements.



General Director Pham Tien Hung participated in the ribbon cutting ceremony of Steam Turbine #2 Casing Lifting Ceremony

Speaking at the ceremony, Mr Nguyen Tai Anh – Deputy General Director of EVN and Deputy General Director of Hyundai Group thanked and appreciated the cooperation of Contractors including Bach Dang Construction Corporation. The construction Companies under Bach Dang Construction Corporation are trying to make efforts to complete items of the main Contract in December of 2013 according to schedule with high quality and absolute safety.

General Director Pham Tien Hung took a souvenir photo with the Owner and General Contractor
 
General Director Pham Tien Hung was inspecting the construction site of  Mong Duong 1 Thermal Power Plant