General Director of BDCC Inspected Construction Site of Mong Duong 1 Thermal Power Plant Project and directed the recovery works after Typhoon Haiya


General Director Pham Tien Hung and Huyndai contractor representatives inspected the  construction site

After construction site inspection and the meeting with Hyundai general contractor, General Director worked with construction Companies for the items of Civil Package A and Building A. Up till now, the Civil Package A has reached 128,3 billion VND, exceeding the plan as required. Building package A has reached 67 billion VND. Bach Dang Construction Joint Stock Company No.201, Bach Dang 234 Construction Joint Stock Company and Bach Dang 5 Joint Stock Company were required to continue to increase manpower, equipment and catch up the progress target to ensure the project’s overall progress.

At the meeting, the Project Management Board was requested to recover quickly from typhoon damage, office and housing stability to ensure construction works in accordance to requirement of the project.

Some images of  BDCC’s General Director inspecting the construction site

Free Porn